Provide support for CEC Lightning upgrade testing [CR 329]

CEC Lightning Upgrade testing will require integrations with inContact to be in place for at least one non-production environment for multiple phases of testing (i.e. Regression, UAT).
More information will be added to this CR on Friday, 2/17, before it is sent over to ASI for planning purposes.?
Priority High
Contact Center(s) VSC, PSC, GRC
Needed By Jun 9, 2023
Closure Date May 26, 2023
  • Attach files
  • Admin
    Christie Jensen
    Reply
    |
    Apr 14, 2023

    Status Notes

    4.14 Identified issues with test patient calls and ticketed to GSK Telco.

    New request to have transfer IVR properly pop cases - working on that - projected fix during Tuesday night maintenance window. Issue also involves reskill of calls.

    1-May-2023 - Carol - Two remaining items for testing.

    5-May-2023 - Testing complete with one outstanding request that needs confirmation.

    19-May-2023 - Roll-out scheduled for Friday, June 9th with a staffed testing window on the 10th. Go live is Monday, June 12th.

    26-May-2023 - Received closure agreement from Carol.